01. Target = 60 ÷ ( SMV x No. of worker x working hour x expected efficiency) .
02. Target = 60÷SMV.
03. Team target =(60÷SMV)x Present operator x Organization efficiency .
04. Target per day = Working hour x 60 x No. of operator / Target SMV.
05. Capacity=Average of total obserb time x 1.66 + 30% Allowance / 60.
06. Factory capacity=No. of operator x working minutes + Present % x average factory efficiency.
07. Capacity per day = Present operator x working hour x organization efficiency x Attendance.
08. Weekly capacity = No. of operators x Absenteesm x Clock minutes per week x Average factory efficiency.
09. Marker efficiency = Area of patterns in the marker / Total area of the marker x 100.
10. Load = (Contract size x work content) contract 1+ (Contract size x work content)
Contract 2 + etc.
11. Load = Order quantity x Work content (SMV of garments).
12. Observe time = Total cycle time / No. of cycle.
13. Basic time = Avarage of observe time X Rating %.
14. Sam = Basic time x Allowance.
15. Rating = Observe time x Standard rating / Standard rating.
16. Cycle time = 60 / Team target.
17. Pitch time = Total SMV / Present operator.
18. Efficiency = Earn hour / Available hour x 100
19. Efficiency = SMV / Total time.
20. Earn hour = (Production x SMV) / 60.
21. Available hour = Working hour x Use machine(Total manpower)
22. Performance = (Earn hour / Available hour – Off standard time) x 100.
23. Improvement = 1-(Production / Capacity).
24. Balancing efficiency = 1-Balancing loss.
25. Loss pcs = (60/SMV)x Available hours x avg factory effi (61%) -Q.C Pass
26. Balancing loss = AML-TML/AMLx100.
27. Standard time = Net operation time x (1+ Ratio of loss time).
28. Daily output = Working hours (seconds) + Standard time.
29. Output per operator = Work hours (second) / Total time of operations.
30. Required No. of operators = Targeted daily output / Daily output per operator.
31. Target daily capacity = Daily work hours / Standard process time (SPT).
32. Daily capacity per worker = Daily capacity / No. of workers = Daily Work hours / Standard total processing.
33. Organization efficiency = Pitch time / Bottle neck process time (x100) = 100/140 x 100 = 71.4%
34. Upper limit = Pitch time / Target organization efficiency = 100 / 0.85 = 117.6 seconds.
35. Lower limit = 2 x Pitch time – Upper limit = 2 x 100 – 117.6 = 82.4 seconds.
36. Planned daily work flow = Daily work hours / Standard process time (SPT) x organization efficiency.
37. Accumulated avarage time = Daily work hours/AccumulatedxNo.of daysxstandard No.of workers in
The group/No. of pieces produced.
38. SMV = Basic time + Allowance time + bundle time.
39. DHU = No. of deffect observe / No. of garments checked.
39. Booking fabric K.G. = Order quantity / 12 x Fabric consumption per doz.
40. Garments K.G. = Total receive fabric kg – (Save return kg + Jhute kg + Wastage fabric kg)
40. Input to sewing pcs. = Total in pcs – (Print Embroidery short & wastage + Cutting wastage pcs.)
39. Fabric consumption (CM) = Length x chest x 2 x GSM / 1000 / 10000 x 12 + Wastage%.
41. Fabric consumption (Inch) = Length x chest x 2 x GSM / 1000 / 1550 x 12 + Wastage%.
Formula#1: Calculating the daily
production target of a line
Daily Line Target = (Total shift hours X 60 X No. of operators in
a line X Line Efficiency%)/Garment SAM
Here is an example to understand this calculation.
Daily shift Hours of a factory = 8 Hours
Number of operators working in that line= 30 operators
Average Efficiency of that line: 60%
Garment SAM: 20 Minutes
Production target of this line (Daily) = (8 X 60 X 30 X60%)/20
=(480 x 30 x60) / (100
X20)
= 432 Pieces
Formula#2: Operator-wise production
target calculation
Individual operator target = (Total working minutes in a day X
Line Efficiency %)/Operation SAM
In Formula #1, you have the formula for calculating the daily
production target for a line.
But operators working in that line will be working on different
operations and the SAM of those operations will be different.
So, you need to calculate individual operator targets as well
based on Line efficiency and operation SAM.
Refer to this example for the calculation operator target for
the specific line.
Factory shift: 8 Hours (480 Minutes)
Line efficiency = 60% (considering it is the same line in
formula#1)
Operation SAM: 0.5 Minutes
Production target of that operator: (480 Minutes x 60%)/0.50
= (480 X 0.60)/0.5
= 576 Pieces per 8
hours per day.
In case you use operator performance level (efficiency%) and
operation SAM and calculate the production target of that operator, the result
is called the operator's production capacity.
Normally, an operator-wise target is not given based on the
individual operators' performance, instead, it is calculated based on the line
efficiency. See the below example of the operator's capacity.
Factory shift: 8 Hours (480 Minutes)
Operator efficiency = 80%
Operation SAM: 0.5 Minutes
Production capacity of that operator: (480 Minutes x 80%)/0.50
= (480 X 0.80)/0.5
= 768 Pieces per 8
hours per day.
Formula#3: Calculating operator
efficiency
Individual operator Efficiency% = (Units Produced X Operation
SAM X 100)/Total minutes worked
When you develop the skill matrix for sewing operators you need
to measure individual performance.
Secondly, if you plan to start a performance-based incentive
scheme for the individual operator, measuring individual operator efficiency is
essential.
Example:
Let's say you need to calculate the efficiency of an operator
based on the last production day's data.
Operator Produced total unit: 500 pieces
SAM of the operation: 0.60 Minutes
The operator worked: 480 Minutes (full shift hours)
Operator Efficiency =
((500 x 0.60)/480 )X100
=(300/480)*100
=62.50%
Formula#4: Line efficiency
Line Efficiency% = (Line output X Garment SAM X 100)/(Number of
operators X Minute worked in a day)
Note: Include helpers and workers doing manual operations in
case you have included SAM of those operations.
Example:
Line A produced 600 units (Style Z)
SAM of style Z is 20 Minutes
Attendance in Line A = 30 Operators
Shift Time: 8 Hours
Line Efficiency (Overall Efficiency%)= (600 x 20 x 100)/(30X8
x60)
= (1200000/14400)
= 83.33%
Here is another example of line efficiency calculation.
Note: include helpers and workers doing manual operations in
case you have included SAM of those operations
Formula#5: Machine productivity
Machine Productivity: (Line output / No. of machine used in
producing those garments)
Machine productivity is measured in production per machine per
shift day. I have discussed more about machine productivity calculation with
examples.
Example:
Considering Line A has production of 600 units.
Numer of sewing machines used: 27 Machines
Machine productivity:
= (600/27)
= 22.22 units per machine
Formula#6: Labour
productivity
Labor Productivity = Line output / No. of total manpower
(operators +helpers)
Example:
Considering Line-A has production of 600 units
Numer of sewing operators used: 30 and helpers 5. Therefore labor productivity
= (600/35)
= 17.14 units per labor
Formula#7:
Line WIP (work in process) = Total pieces lying on the line for a particular order
line
WIP of the line of an order is equal to the total pieces loaded
till date minus Total pieces out till date.
Formula#8:
Standard Time = (Observed time X observed rating) + Allowances
Allowances – Relaxation allowance, contingency allowance
Formula#9:
Machine utilization% = (Actual Machine running Time X 100) /
Time available
Formula#10:
Cost per minute = Total cost incurred in labor / Total available
working minute in a day X no. of labors
Formula#11:
Production Cost per unit = Total cost incurred in production in
a day/ no. of garment produced in a day
Formula#12:
Man to Machine ratio = Total manpower of the factory / Total no.
of sewing machines (utilized)
24 Industrial Engineering (IE)
Formula for Garments Industry
01. Determination of SAM (Standard Allowed Minute): SAM =
(Cycle Time × Performance Rating) + Allowances
- Cycle Time:
75
- Performance
Rating: 75%
- Allowances:
10
- SAM
(Standard Allowed Minute): 1.10
02. Determination of SMV (Standard Minute Value): SMV =
Cycle Time × Performance Rating
- Cycle Time:
30
- Performance
Rating: 85%
- SMV
(Standard Minute Value): 0.43
03. Determination of Earned Minute: Earned Minute = Total
Production X SMV
- Total
Production: 1700 pcs
- SMV: 5.20
- Earned
Minute: 840.00
04. Determination of CPM (Cost Per Minute) CPM (Cost Per
Minute) = Monthly Factory Cost/Monthly Earned Minute
- Monthly
Factory Cost: 12000000
- Monthly
Earned Minute:1120000
- CPM (Cost
Per Minute):10.71
05. Determination of CM (Cost of Manufacturing): Cost of
Manufacturing (CM) = SMV × CPM
- SMV: 5.5
- CPM: 10.7
- CM (Cost of
Manufacturing): 58.85
06. Determination of Daily Line Target Daily
Line Target = (Working Minute × Manpower × Efficiency)/SMV
- Working
Minute/Hour: 600 Minute
- Manpower:
35
- Efficiency:
50%
- SMV: 7.8
- Daily Line
Target: 1346
07. Determination of Individual Operator Target:
Individual Operator Target = (Working Minute × Manpower × Efficiency)/SMV
- Working
Minute/Hour: 600 Minute
- Manpower: 1
- Efficiency:
60%
- SMV: 0.25
- Individual
Operator Target: 1440
08. Determination of Line Efficiency: Line Efficiency =
(Line Output × SMV × 100)/ (Manpower × Working Minute)
- Line
Output: 2200
- SMV: 12.5
- Manpower:
60 persons
- Working
Minute/Hour: 700 Minute
- Daily
Individual Line Target: 65%
09. Determination of Individual Operator Efficiency:
Individual Operator Efficiency = (Line Output × SMV × 100)/ (Manpower ×Working
Minute)
- Line
Output: 1400
- SMV: 0.3
- Manpower: 1
Person
- Working
Minute/Hour: 600 Minute
- Individual
Operator Efficiency: 70%
10. Determination of Production Cost Per Unit: Production
Cost Per Unit = Total Production Cost/Total Production Pcs
- Total
Production Cost: 72000
- Total
Production Pcs: 1500
- Production
Cost Per Unit:
48
11. Determination of Machine Productivity: Machine
Productivity = Total Output/Total Machine
- Total
Output: 2000
- Total
Machine: 25
- Machine
Productivity: 80
12. Determination of Labor Productivity: Labor
Productivity = Total Output/Labor (Manpower)
- Total
Output: 1500
- Labor
(Manpower): 32
- Labor
Productivity: 47
13. Determination of Machine Utilization (%): Machine
Utilization (%) = (Actual Machine Run Time X 100) / Total Time
- Total Time:
600
- Actual
Machine Run Time: 400
- Machine
Utilization (%): 67%
14. Determination of Man to Machine Ratio (MMR): Machine
to Machine Ratio (MMR) = Total Manpower/Total Number of Machines
- Total
Manpower: 4000
- Total
No-Idle Machine: 2600
- Man to
Machine Ratio (MMR): 1.54
15. Determination of Monthly Factory Capacity: Factory
capacity = (Working Hour × Total Worker × Working Day × Factory Efficiency × 60)/Avg.
SMV
- Working
Hour: 10
- Total
Worker: 2500
- Working
Day: 27
- Factory
Efficiency: 55%
- Factory
Average SMV: 5.5
- Factory
Capacity: 4050000
16. Determination of Cut to Ship Ratio: Cut to Ship Ratio
= (Total Shipped Quantity/Total Cut Quantity) × 100
- Total Shipped
Quantity: 4000000
- Total Cut
Quantity: 4080000
- Cut to Ship
Ratio: 98%
17. Determination of Cut to Ship Loss: Cut to Ship Loss
(%) = [(𝑇𝑜𝑡𝑎𝑙 C𝑢𝑡 Qty.- 𝑇𝑜𝑡𝑎𝑙 Ship Qty.)/ 𝑇𝑜𝑡𝑎𝑙 C𝑢𝑡 Qty.] × 100
- Total
Shipped Quantity: 4000000
- Total Cut
Quantity: 4080000
- Cut to Ship
Ratio: 2%
18. Determination of Total Financial Saving: Total
Financial Saving = Number of Extra Pieces Shipped × Average FOB
- Number of
Extra Pieces Shipped: 1000
- Average
FOB: 4.5
- Cut to
Financial Saving: 4500
19. Determination of DHU (Defect Per Hundred Unit): DHU =
(Total Number of Defects Found × 100)/Total Pieces Checked
- Total
Pieces Checked: 1100
- Total
Number of Defects Found: 85
- DHU (Defect
Per Hundred Units): 7.73
20. Determination of Pitch Time: Pitch Time = Garments
SMV/No. of Operations
- Garments
SAM: 9.8
- No. of
Operation: 25
- Pitch Time:
0.39
21. Determination of WIP (Work in progress) = Total input-
Total output (cutting/sewing/finishing)
- Total
input: 1775 pcs
- Total
output: 970 pcs
- WIP: 805
pcs
22. Determination of RFT (Right First time) = (Number of
pass goods or Lot / Number of total produced goods or Lot) x 100
- Total pass:
195 pcs
- Total
Produced: 203 pcs
- RFT: 95.06
%
23. Formula of calculating Defective Rate = (Total
defective garments /Total inspected garments) *100
- Total
defective garments: 17 pcs
- Total
inspected: 307 pcs
- Defective
Rate: 5.53 %
24. Formula of calculating Defects Rate = (Total defects
/Total inspected garments) *100 (One garment may have more than one defect)
- Total
defects in inspected garments: 22 pcs
- Total
inspected: 307 pcs
- Defects
Rate: 7.16 %
.jpeg)
.png)